THIS WEEK'S ACCOMPLISHMENT

    Completed CMU work
    Dried in roof
    Started Low Voltage rough
    Passed Electric Rough at 3rd level
    Fireproof 1st coat of garage ceiling
    Started 2nd Floor door frames

Garage Fireproofing

NEXT WEEK'S ACTIVITIES

    Completed CMU work
    Dried in roof
    Started Low Voltage rough
    Passed Electric Rough at 3rd level
    Fireproof 1st coat of garage ceiling
    Started 2nd Floor door frames

Near Top Out

27th St. Exit