Weekly Project Update
Alpha Nu Chapter of Sigma Chi Fraternity
THIS WEEK'S ACCOMPLISHMENT
- Completed CMU work
- Dried in roof
- Started Low Voltage rough
- Passed Electric Rough at 3rd level
- Fireproof 1st coat of garage ceiling
- Started 2nd Floor door frames
Garage Fireproofing
NEXT WEEK'S ACTIVITIES
- Completed CMU work
- Dried in roof
- Started Low Voltage rough
- Passed Electric Rough at 3rd level
- Fireproof 1st coat of garage ceiling
- Started 2nd Floor door frames
Near Top Out
27th St. Exit