Weekly Project Update
Integral Care
1/7
THIS WEEK'S ACCOMPLISHMENT
- New Layout for Millwork in each room was Approved by Architect and laid out on the floor so Electrical and Plumbing rough in to begin
- New 3rd floor electrical layout rough in is complete and inspection called in.
- New 2nd floor electrical layout rough in is complete and inspection called in.
- Roofer completed demo of roof shingles and installation of new roof shingles.
1/7
- Plumber identified plumbing issues and has a list repairs. they also started plumbing top out rough in on new millwork layout.
- Plumbing inspection on rooms 126, 226,and 326 passed.
Rooms 126, 226, and 326 pass Plumbing inspection
NEXT WEEK'S ACTIVITIES
- Electrical inspection will be completed.
- Plumbing top out rough in on 2nd floor will be complete.
- Framer subcontractor will bring in LVL to get climatized for the room 206.
- Gyp board material will be brought in to site and stacked inside the building
-
-
1/7
Concrete repair for Plumbing rough in complete
1/7
New Electrical layout for approved millwork layout