Weekly Project Update

Agilent 2nd Floor Renovations 2/16/2023

Placeholder

Michael Olmos

THIS WEEK'S ACCOMPLISHMENT

    framed new walls for restroom 204
    framed wall between Office 206 and Conference Room 207
    relocated door 205
    removed plumbing fixtures
    first coat of paint on walls in the existing large cubicle areas
    demo'd ceramic tile out of existing restroom 203
Excavation 1.jpg

metal studs for restroom 204 walls framed

NEXT WEEK'S ACTIVITIES

    frame 6 inch wall between restrooms 203 and 204
    electric rough in
    install ceiling grid in existing large cubicle areas
    plumbing rough in
    rough in data ports
Excavation 1.jpg

framed door 207 for new conference room

Excavation 1.jpg

relocated door 205 for existing large conference room

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.