top of page


Weekly Project Update
Agilent 2nd Floor Renovations 2/16/2023

Michael Olmos
THIS WEEK'S ACCOMPLISHMENT
- framed new walls for restroom 204
- framed wall between Office 206 and Conference Room 207
- relocated door 205
- removed plumbing fixtures
- first coat of paint on walls in the existing large cubicle areas
- demo'd ceramic tile out of existing restroom 203

metal studs for restroom 204 walls framed
NEXT WEEK'S ACTIVITIES
- frame 6 inch wall between restrooms 203 and 204
- electric rough in
- install ceiling grid in existing large cubicle areas
- plumbing rough in
- rough in data ports

-
framed door 207 for new conference room

relocated door 205 for existing large conference room
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page