Weekly Project Update
Agilent 2nd Floor Renovations 2/23/2023

Michael Olmos
THIS WEEK'S ACCOMPLISHMENT
- framed 6 inch wall between restrooms 203 & 204
- installed ceiling grid in large cubicle areas
- sheetrocked inside walls for restrooms 209 & 210
- reinstalled door 201 and sheetrocked half wall at new break area 202
- electric rough in, began laying 2x2 lights into completed grid
- laid A/C grills into completed grid

Door 201 reinstalled and half wall by break area 202 sheetrocked
NEXT WEEK'S ACTIVITIES
- begin ceramic tile installation in restrooms 209/210
- install sheetrock and perform all patches
- begin tape, float, and texture on new walls
- install 2x2 light fixtures into completed grid
- core 6 inch holes in floor for power to future cubicles/furniture

-
6 inch wall between restrooms 203 and 204 framed

installed ceiling grid in large cubicle areas with 2x2 lights laid in
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.