Weekly Project Update

Agilent 2nd Floor Renovations 2/23/2023

Placeholder

Michael Olmos

THIS WEEK'S ACCOMPLISHMENT

    framed 6 inch wall between restrooms 203 & 204
    installed ceiling grid in large cubicle areas
    sheetrocked inside walls for restrooms 209 & 210
    reinstalled door 201 and sheetrocked half wall at new break area 202
    electric rough in, began laying 2x2 lights into completed grid
    laid A/C grills into completed grid
Excavation 1.jpg

Door 201 reinstalled and half wall by break area 202 sheetrocked

NEXT WEEK'S ACTIVITIES

    begin ceramic tile installation in restrooms 209/210
    install sheetrock and perform all patches
    begin tape, float, and texture on new walls
    install 2x2 light fixtures into completed grid
    core 6 inch holes in floor for power to future cubicles/furniture
Excavation 1.jpg

6 inch wall between restrooms 203 and 204 framed

Excavation 1.jpg

installed ceiling grid in large cubicle areas with 2x2 lights laid in

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.