Weekly Project Update

Agilent 2nd Floor Renovations 3/9/2023

Placeholder

Michael Olmos

THIS WEEK'S ACCOMPLISHMENT

    Finished installation of all sheetrock
    Finished tape, float, texture and first coat of all new walls
    Installed new exhaust fan in restroom 204
    Finished installation of ceramic tile in restrooms 209/210
    Finished installation of 2x2 ceiling tile in existing large conference room
    Started installation of remaining 2x2 ceiling grid in new restrooms 203/204, new work area, 202 break area, office 206, and new Conference Room 207
Excavation 1.jpg

Exhaust fan in new restroom 204

NEXT WEEK'S ACTIVITIES

    Finish installation of all 2x2 ceiling grid
    Finish installing 2x2 light fixtures in remaining areas
    Finish reinstallation of all HVAC supply and return grills
    Finish sprinkler head relocation
    Finish polished concrete floor finish in 208 break area, 202 break area, and 203/204 restrooms
Excavation 1.jpg

New ceiling tile installed in large conference room

Excavation 1.jpg

Finished installation of ceramic tile and grout in restrooms 209/210

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.