BB-construction logo_PMS_edited.png

Weekly Project Update

Alpha Nu Chapter Sigma Chi Fraternity House

Placeholder

Greg Berlin

THIS WEEK'S ACCOMPLISHMENT

    COMPLETED BUILDING/ROOF INSULATION
    PASSED BUILDING FINAL INSULATION INSPECTION
    COMPLETED FIRE TAPING ABOVE CEILING FOR 2ND AND 3RD FLOORS
    INSTALLED REMAINING WINDOWS AT NORTH STAIRWELL
    COMPLETED EAST ELEVATION GRADE WORK
    INSTALLED 8X8 SUPPORTS AT WEST ELEVATION
Excavation 1.jpg

SPRAY FOAM INSULATION AT ROOF DECK

NEXT WEEK'S ACTIVITIES

    INSTALL 1ST FLOOR DOOR FRAMES
    COMPLETED HARDI SIDING AT 1ST FLOOR LOBBY
    POUR EAST ELEVATION FLAT WORK AND GARAGE ENTRANCE
    BEGIN SHEETROCK CEILINGS AT 2ND FLOOR ABOVE FCU FUR-DOWN
    PRESSURE TEST 1ST AND 2ND FLOOR FIRE SPRINKLERS
    BEGIN QUARRY TILE INSTALLATION
Excavation 1.jpg

EXTERIOR ELECTRICAL PANELS AT MECHANICAL PLATFORMS

Excavation 1.jpg

8X8 SUPPORTS AT WEST ELEVATION

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.