Weekly Project Update

Alpha Nu Chapter Sigma Chi Fraternity House

Greg Berlin

THIS WEEK'S ACCOMPLISHMENT

    Completed 3rd Floor Door Frame Installation
    Installed Blocking at Elevator Shaft
    Began Sheetrock at South Stairwell and Elevator Shaft
    Installed Connection Brackets for Stairs at South Stairwell
    Began Fire Sprinkler piping at 3rd Floor
    Completed Low Voltage Data Rough in

Hardi Siding at West Elevation

NEXT WEEK'S ACTIVITIES

    Frame Over North Stairwell and Complete Roof Dry in
    Continue Sheet Rock at 3rd and 4th Floors
    Frame Fire Dampers and access panels
    Complete Sheetrock at South Stairwell and Elevator Shaft
    Continue insulation at 4th Floor
    Deliver Asphalt Shingles

North Stairwell at Attic Level

Hardi Siding South East Elevation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.