THIS WEEK'S ACCOMPLISHMENT

    ELECTRICAL AND MECHANICAL CONNECTIONS TO HVAC ROOM CASSETTES
    INSTALL DROP CEILING ASSEMBLIES 2ND FLOOR
    FIRE TAPE AND DRAFT STOP AT 1ST, 2ND FLOOR & ELEVATOR
    COMPLETE 2ND & 3RD BATHROOM FLOOR TILE
    COMPLETE TAPE AND FLOAT OF WALLS AT 1ST, 2ND & 3RD FLOORS
Excavation 1.jpg

CEILING FURR DOWNS

NEXT WEEK'S ACTIVITIES

    1ST & 2ND ELECTRICAL ROUGH IN DROP CEILINGS
    1ST & 2ND MECHANICAL ROUGH AT DROP CEILINGS
    IRE SPRINKLER PIPING INSPECTION 3RD & 4TH FLOORS
    HAT CHANNEL & SHEETROCK 4TH FLOOR CEILINGS
    SHOWER WALL TILE 2ND & 3RD FLOORS
    START PAINT OF WALLS AT 2ND & 3RD FLOORS
Excavation 1.jpg

BATHROOM TILE FLOORS

Excavation 1.jpg

BEDROOM WALL PAINT

LOOK AHEAD SCHEDULE