THIS WEEK'S ACCOMPLISHMENT

    CMU Detail work at windows and doors North Stair Tower
    Installed Tyvek waterproofing at 4th and top Level
    Flashed Window Openings.
    Passed Plumbing Rough and Electric Rough at 2nd Level
    Completed over frame at Elevator
    Completed Decking and Fascia at South end of Building

North Stairwell West

NEXT WEEK'S ACTIVITIES

    Install windows
    Fire Proof garage ceiling
    Dry in building / install roofing underlayment
    Plumber working starting 4th floor supply and finishing Drain and Waste lines
    Electrician rough on 3rd floor walls and work towards inspection
    Framer to working on blocking and hardware installation

Garage Parking

West Elev

LOOK AHEAD SCHEDULE