THIS WEEK'S ACCOMPLISHMENT

    PASSED MECHANICAL ROUGH INSPECTION 4TH FLOOR
    SHEET ROCK 4TH FLOOR DROP CEILINGS
    FRAME DROP CEILINGS AT THE 3RD FLOOR
    INSTALLED 2” WATER SERVICE AND WASTEWATER LINES
    START ELEVATOR INSTALL
Excavation 1.jpg

Elevator install going up

NEXT WEEK'S ACTIVITIES

    RESTART EXT. PAINTING
    PAINT INTERIOR 1ST AND 2ND FLOORS
    TAPE FLOAT TEXTURE 4TH FLOOR CEILINGS
    MECH ROUGH OF DROP CEILINGS AT 3RD FLOOR
    INSTALL FIRE LINE BACK FLOW PREVENTER AT BELOW GRADE VAULT
Excavation 1.jpg

Mechanical platform level 4

Excavation 1.jpg

Overnight install of 8" water tap below grade on 27th St.

LOOK AHEAD SCHEDULE