Weekly Project Update

Alpha Nu Sigma Chi Fraternity

Greg Berlin

THIS WEEK'S ACCOMPLISHMENT

    Poured 225 yards of Concrete
    Wreck Forms and cleaned up site
    Poured Electric Vault footing
    Started Vertical Construction of CMU

Steel & Concrete Pre-pour

NEXT WEEK'S ACTIVITIES

    Continue CMU Installation
    Rough Grade Site
    Install CMU Door Frames at 1st Level
    Continue 3rd Party testing of CMU Grout and Mortar

Concrete Pour 0500 11.09.2020

Garage Floor level 1

LOOK AHEAD SCHEDULE