Weekly Project Update
BBTCS Marble Falls Renovations 1/13/2023

Michael Olmos
THIS WEEK'S ACCOMPLISHMENT
- demo'd Area 3 flooring
- completed first coat of paint in Area 3
- completed second coat of paint in Area 3
- installed new flooring and cove base in Area 3
- installed new room signage and new reception logo in Area 1
- completed installation of "A" fixtures in Area 3

New carpet flooring in Area 3 office
NEXT WEEK'S ACTIVITIES
- complete final clean of project
- get final inspection from City of Marble Falls
- complete all punch list items
-
-

-
Accent wall in Area 3 Conference Room

New logo sign in Area 1 reception
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.