Weekly Project Update

BBTCS Marble Falls Renovations 1/13/2023

Placeholder

Michael Olmos

THIS WEEK'S ACCOMPLISHMENT

    demo'd Area 3 flooring
    completed first coat of paint in Area 3
    completed second coat of paint in Area 3
    installed new flooring and cove base in Area 3
    installed new room signage and new reception logo in Area 1
    completed installation of "A" fixtures in Area 3
Excavation 1.jpg

New carpet flooring in Area 3 office

NEXT WEEK'S ACTIVITIES

    complete final clean of project
    get final inspection from City of Marble Falls
    complete all punch list items
Excavation 1.jpg

Accent wall in Area 3 Conference Room

Excavation 1.jpg

New logo sign in Area 1 reception

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.