top of page


Weekly Project Update
BBTCS Marble Falls Renovations 1/6/2023

Michael Olmos
THIS WEEK'S ACCOMPLISHMENT
- installed Area 2 transaction window and door lights
- installed cove base
- final coat of paint performed
- all door hardware completed
- relocated Area 2 sprinkler heads and A/C ducts
- performed final clean of Area 2

can lights, A/C supply, fire detector, and sprinkler head installed in ceiling
NEXT WEEK'S ACTIVITIES
- demo Area 3 flooring
- perform first coat of paint in Area 3
- perform final coat of paint in Area 3
- install new flooring and cove base in Area 3
- switch out remaining 2x4 lights in Area 3

- install new room signage and new logo sign in Area 1
locks on medical cabinets installed

Area 2 transaction window installed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page