Weekly Project Update

BBTCS Marble Falls Renovations 1/6/2023

Placeholder

Michael Olmos

THIS WEEK'S ACCOMPLISHMENT

    installed Area 2 transaction window and door lights
    installed cove base
    final coat of paint performed
    all door hardware completed
    relocated Area 2 sprinkler heads and A/C ducts
    performed final clean of Area 2
Excavation 1.jpg

can lights, A/C supply, fire detector, and sprinkler head installed in ceiling

NEXT WEEK'S ACTIVITIES

    demo Area 3 flooring
    perform first coat of paint in Area 3
    perform final coat of paint in Area 3
    install new flooring and cove base in Area 3
    switch out remaining 2x4 lights in Area 3
Excavation 1.jpg
    install new room signage and new logo sign in Area 1

locks on medical cabinets installed

Excavation 1.jpg

Area 2 transaction window installed

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.