Weekly Project Update

BBTCS Marble Falls Renovations 10/28/2022

Placeholder

Michael Olmos

THIS WEEK'S ACCOMPLISHMENT

    set reception and waiting area light fixtures
    relocated Area 1 sprinkler heads
    reset Area 1 exit signs
    passed electrical above ceiling inspection
Excavation 1.jpg

Can light, A/C supply, and sprinkler head all set in new ceiling grid

NEXT WEEK'S ACTIVITIES

    reinstall fire devices in ceilings
    install lighting trim for Area 1
    remove and replace restroom countertops
    install ceiling tile
    final coat of paint
Excavation 1.jpg
    install cove base

New reception lighting set

Excavation 1.jpg

Can lights for waiting area installed

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.