Weekly Project Update
BBTCS Marble Falls Renovations 10/28/2022

Michael Olmos
THIS WEEK'S ACCOMPLISHMENT
- set reception and waiting area light fixtures
- relocated Area 1 sprinkler heads
- reset Area 1 exit signs
- passed electrical above ceiling inspection
-
-

Can light, A/C supply, and sprinkler head all set in new ceiling grid
NEXT WEEK'S ACTIVITIES
- reinstall fire devices in ceilings
- install lighting trim for Area 1
- remove and replace restroom countertops
- install ceiling tile
- final coat of paint

- install cove base
New reception lighting set

Can lights for waiting area installed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.