THIS WEEK'S ACCOMPLISHMENT

    installed all door lights
    installed Area 1 transaction window
    completed Area 1 reception desks
    moved staff back into Area 1
    framed Area 2 transaction window
    completed all Area 2 demo
Excavation 1.jpg

framed Area 2 transaction window

NEXT WEEK'S ACTIVITIES

    demo Area 2 flooring
    complete Area 2 tape, float, texture and first coat
    install ceiling grid in Area 2 Conference Room
    Area 2 duct relocation
    Area 2 sprinkler head relocation
Excavation 1.jpg
    begin installing can lights in Area 2 conference room

Completed Area 1 transaction window

Excavation 1.jpg

Completed Area 1 Reception

LOOK AHEAD SCHEDULE