Weekly Project Update
BBTCS Marble Falls Renovations 12/16/2022

Michael Olmos
THIS WEEK'S ACCOMPLISHMENT
- installed all door lights
- installed Area 1 transaction window
- completed Area 1 reception desks
- moved staff back into Area 1
- framed Area 2 transaction window
- completed all Area 2 demo

framed Area 2 transaction window
NEXT WEEK'S ACTIVITIES
- demo Area 2 flooring
- complete Area 2 tape, float, texture and first coat
- install ceiling grid in Area 2 Conference Room
- Area 2 duct relocation
- Area 2 sprinkler head relocation

- begin installing can lights in Area 2 conference room
Completed Area 1 transaction window

Completed Area 1 Reception
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.