Weekly Project Update

BBTCS Marble Falls Renovations 12/2/2022

Placeholder

Michael Olmos

THIS WEEK'S ACCOMPLISHMENT

    installed all "F" light fixtures throughout building
    installed all Area 1 lighting controls
    installed all Area 1 "A/AE" light fixtures
    tall reception cabinet installed, medical storage room millwork installed, reception desks 85% complete
    began demo in Area 2 for future conference room
Excavation 1.jpg

Front of Reception

NEXT WEEK'S ACTIVITIES

    complete installation of all "A/AE" fixtures throughout Areas 2 & 3
    complete reception
    final coat 1x2 trim in reception
    complete demo in future Area 2 conference room
    begin floor demo in Area 2
Excavation 1.jpg
    begin framing for Area 2 conference room

Millwork in medical storage room

Excavation 1.jpg

Area 1 lighting control

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.