Weekly Project Update
BBTCS Marble Falls Renovations 12/2/2022

Michael Olmos
THIS WEEK'S ACCOMPLISHMENT
- installed all "F" light fixtures throughout building
- installed all Area 1 lighting controls
- installed all Area 1 "A/AE" light fixtures
- tall reception cabinet installed, medical storage room millwork installed, reception desks 85% complete
- began demo in Area 2 for future conference room
-

Front of Reception
NEXT WEEK'S ACTIVITIES
- complete installation of all "A/AE" fixtures throughout Areas 2 & 3
- complete reception
- final coat 1x2 trim in reception
- complete demo in future Area 2 conference room
- begin floor demo in Area 2

- begin framing for Area 2 conference room
Millwork in medical storage room

Area 1 lighting control
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.