top of page


Weekly Project Update
BBTCS Marble Falls Renovations 12/9/2022

Michael Olmos
THIS WEEK'S ACCOMPLISHMENT
- final coat reception
- install quartz countertops in reception
- install doors and hardware
- complete Area 2 Conference Room demo
- framing and sheetrock installation for Area 2 complete
- 95% of all new light fixtures throughout building installed

Area 2 double door frame
NEXT WEEK'S ACTIVITIES
- complete Area 1, perform final clean for area
- tape, float, texture and first coat Area 2
- install ceiling grid in Area 2 Conference Room
- demo Area 2 flooring
-

-
Final coat of paint in reception

Quartz countertops in Reception
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page