Weekly Project Update

BBTCS Marble Falls Renovations 12/9/2022

Placeholder

Michael Olmos

THIS WEEK'S ACCOMPLISHMENT

    final coat reception
    install quartz countertops in reception
    install doors and hardware
    complete Area 2 Conference Room demo
    framing and sheetrock installation for Area 2 complete
    95% of all new light fixtures throughout building installed
Excavation 1.jpg

Area 2 double door frame

NEXT WEEK'S ACTIVITIES

    complete Area 1, perform final clean for area
    tape, float, texture and first coat Area 2
    install ceiling grid in Area 2 Conference Room
    demo Area 2 flooring
Excavation 1.jpg

Final coat of paint in reception

Excavation 1.jpg

Quartz countertops in Reception

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.