Weekly Project Update

BBTCS Marble Falls Renovations 9/9/2022

Placeholder

Michael Olmos

THIS WEEK'S ACCOMPLISHMENT

    first coat of paint in Area 1 offices, corridors, and restrooms
    LVT flooring installed in Area 1 corridors
    Carpet Flooring installed in Area 1 offices
    Framing for new Telemed offices and Reception wall
Excavation 1.jpg

LVT flooring in Area 1 hallways and first coat of paint

NEXT WEEK'S ACTIVITIES

    Area 1 Framing Inspection
    begin Area 1 electrical wall rough
    final coat of paint in Area 1 offices and corridors
    install Area 1 cove base
    demo Storage millwork
Excavation 1.jpg

Carpet flooring in Area 1 offices and first coat of paint

Excavation 1.jpg

Framing for new Telemed offices

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.