THIS WEEK'S ACCOMPLISHMENT

    first coat of P-3 color in Area 1 reception
    Final coat telemed offices and waiting area
    fully installed reception lights and waiting area can lights with trim
    replaced three sprinkler heads in reception
    installed remaining Area 1 cove base
Excavation 1.jpg

Fully installed lights at reception, first coat for ceiling and wall complete

NEXT WEEK'S ACTIVITIES

    install 1x2 wood trim in reception
    begin installation of reception desks
    begin installation of reception shelving
    begin installation of millwork in Area 1 medical storage
    install Area 1 doors and hardware
Excavation 1.jpg

Cove base in telemed office, all Area 1 cove base installed

Excavation 1.jpg

Waiting area ceiling tile, can lights installed with trim

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.