THIS WEEK'S ACCOMPLISHMENT

    demo waiting area walls and ceilings
    demo reception wall and ceiling
    demo Area 1 office and corridor flooring
    demo reception and waiting area flooring
    demo reception and waiting area light fixtures and receptacles
Excavation 1.jpg

Flooring in Area 1 offices and corridor demoed

NEXT WEEK'S ACTIVITIES

    begin framing for new reception walls
    begin framing for new Telemed offices
    paint 1st coat in Area 1 offices and corridor
    begin new flooring installation in Area 1 offices and corridor
Excavation 1.jpg

Reception wall, ceiling, and flooring demoed

Excavation 1.jpg

Waiting area walls, ceilings, and flooring demoed