THIS WEEK'S ACCOMPLISHMENT
- demo waiting area walls and ceilings
- demo reception wall and ceiling
- demo Area 1 office and corridor flooring
- demo reception and waiting area flooring
- demo reception and waiting area light fixtures and receptacles
-

Flooring in Area 1 offices and corridor demoed
NEXT WEEK'S ACTIVITIES
- begin framing for new reception walls
- begin framing for new Telemed offices
- paint 1st coat in Area 1 offices and corridor
- begin new flooring installation in Area 1 offices and corridor
-

-
Reception wall, ceiling, and flooring demoed

Waiting area walls, ceilings, and flooring demoed
LOOK AHEAD SCHEDULE