THIS WEEK'S ACCOMPLISHMENT

    Last of the kitchen exhaust fans arrived and installed
    Classroom wing cleaned so school can wax next week
    Duct 90% control wiring 90% electrical wiring 95%
    Grid and ceiling tile re-installed in classroom wings
    All classroom a/c units up and running except 6 missing condensers.
    Piping and ductwork started on large units office wing. 75% complete.
Excavation 1.jpg

Roof materials staged on roof ready for starting next week

NEXT WEEK'S ACTIVITIES

    Office wing re-installs grid and tile
    Office wing cleans so waxing can start soon after
    Last 6 condensers hook up if they arrive
    Start clearing out cafeteria of materials and equipment.
    Roof repairs start. Two week process but does not effect interior.
Excavation 1.jpg
    High gym and stage grid and tile install. Lifts off job.

Last of the Exhaust Fans arrived and installed.

Excavation 1.jpg

Large units in boiler room arrived and installed.

LOOK AHEAD SCHEDULE