Weekly Project Update
Decker Middle School Kitchen Serving Lines

Keith Farrell
THIS WEEK'S ACCOMPLISHMENT
- Framed Walls
- Electric rough in complete
- Poured concrete at removed floor sinks
- Started plumbing rough in
- Sheetrock one sided
- AC grills reinstalled in ceiling grid

Plumbing rough for floor sinks
NEXT WEEK'S ACTIVITIES
- Finish plumbing Rough in
- Start quarry tile patch
- Complete sheetrock
- Put lights in grid
- Ceramic wall tile patch

- Complete steel under floor
Framing and steel

Sheetrock on one side
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.