Weekly Project Update
Decker Middle School Kitchen Serving Lines

Keith Farrell
THIS WEEK'S ACCOMPLISHMENT
- Patched floor and wall tile
- Finished under floor steel
- Finished Plumbing Rough
- Finished sheetrock
- Set AC grills back in new grid
- Received hand wash sinks

Floor sink
NEXT WEEK'S ACTIVITIES
- Grout tile
- Tape & float sheetrock
- Set hand wash sinks
- Finish ceiling grid & tile
- Mount roll up doors

- Receive serving lines
Wall tile patch

Sheetrock on cafeteria side
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.