top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Decker Middle School Kitchen Serving Lines

Placeholder

Keith Farrell

THIS WEEK'S ACCOMPLISHMENT

    Patched floor and wall tile
    Finished under floor steel
    Finished Plumbing Rough
    Finished sheetrock
    Set AC grills back in new grid
    Received hand wash sinks
Excavation 1.jpg

Floor sink

NEXT WEEK'S ACTIVITIES

    Grout tile
    Tape & float sheetrock
    Set hand wash sinks
    Finish ceiling grid & tile
    Mount roll up doors
Excavation 1.jpg
    Receive serving lines

Wall tile patch

Excavation 1.jpg

Sheetrock on cafeteria side

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page