Weekly Project Update

Del Valle High School Secure Vestibule

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    Completed Tape and Floating Walls and Ceilings
    Began Interior Painting
    Installed Ceiling Grid Framing
    Installed Frames for Aluminum Storefront Windows
Excavation 1.jpg

Painted Walls and Ceiling

NEXT WEEK'S ACTIVITIES

    Complete Painting
    Relocated Fire Sprinklers in Grid Ceiling
    Install Flooring
    Install Millwork
    Install Light Fixtures
Excavation 1.jpg
    Install Aluminum Storefront Glass

Grid Ceiling Framing

Excavation 1.jpg

Painted Walls and Ceiling

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.