Weekly Project Update

FORREST TRAILS PLAYSCAPE IMPROVEMENTS

Placeholder

Pat Tims

THIS WEEK'S ACCOMPLISHMENT

    NEW SURFACE BEGINS 8-2
    LANDSCAPING BEGINS THIS WEEK
Excavation 1.jpg

PLAYSCAPE READY FOR BUFFINGS

NEXT WEEK'S ACTIVITIES

    PLAYSCAPE TO RECEIVE NEW SURFACE
    LANDSCAPING; NEW SOD
    TEMPORARY IRRIGATION
Excavation 1.jpg

PLAYSCAPE READY FOR FINAL SURFACE

Excavation 1.jpg

READY FOR SURFACE

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.