Weekly Project Update
George D Alan

James Castillo
THIS WEEK'S ACCOMPLISHMENT
- Finished installing awnings
- Started installing lights in ceiling grid
- started installing HVAC registers in ceiling grid
- started ceramic tile in rest rooms
-
-

NEXT WEEK'S ACTIVITIES
- Continue ceramic tile work
- continue installing lights in ceiling grid
- continue installing registers in ceiling grid
- Install millwork
- Permanent power to building

-

LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.