Weekly Project Update
HYDE PARK BAPTIST CHURCH - BASEMENT RENOVATION

Nathan Barry
THIS WEEK'S ACCOMPLISHMENT
- Complete Setting Condensers for AHU #9 & AHU #10 on Roof
- Complete Wood Fence Enclosures @ New Mechanical Yards
- Complete Texturing Walls
- Start Prime & 1st Finish Paint @ All Walls
- Continue Pulling Wire in Conduit
- Finalize Color Selections for Ceramic Tile, Wall Paint, Solid Surface Tops & Laminate @ Millwork

New Condensers for AHU #9 & #10, Refrigerant Piping, Existing Kitchen Hood Exhaust Fan
NEXT WEEK'S ACTIVITIES
- Continue Painting @ All Walls
- Continue Ceiling Grid
- Start Plaster Repair
- Start Ceramic Tile Installation
- Continue Electric Wire Installation

- Connect Duct & Refrigerant Lines to AHU 7.1 & AHU 7.2
Painting 1st Finish Coat @ Gathering Room Fur-Downs

New Wood Fencing @ NE Mechanical Yard
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.