Weekly Project Update
HYDE PARK BAPTIST CHURCH - BASEMENT RENOVATION

Nathan Barry
THIS WEEK'S ACCOMPLISHMENT
- Continue Pulling Homerun Wire to Panels
- Receive (2) New Electric Transformers
- Continue Ceiling Grid Throughout Basement
- Start Light Fixture Installation / Turn On
- Receive / Store LVT Flooring & Adhesive
- Start Fire Alarm Wire Installation

Pull Homerun Wire to Panel - Typical
NEXT WEEK'S ACTIVITIES
- Complete Ceiling Grid All Locations
- Continue Light Fixture Installation Throughout
- Complete Fire Alarm Pre-Wire Installation
- Start Ceramic Tile Installation
- Electrical Prep for Shut-Down / Switchgear Installation Starting 11-21

- Continue Refrigerant Piping Extension to Condensers
Start Fire Alarm Pre-Wire Installation

Install Light Fixtures Throughout Basement
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.