THIS WEEK'S ACCOMPLISHMENT

    Continue Pulling Homerun Wire to Panels
    Receive (2) New Electric Transformers
    Continue Ceiling Grid Throughout Basement
    Start Light Fixture Installation / Turn On
    Receive / Store LVT Flooring & Adhesive
    Start Fire Alarm Wire Installation
Excavation 1.jpg

Pull Homerun Wire to Panel - Typical

NEXT WEEK'S ACTIVITIES

    Complete Ceiling Grid All Locations
    Continue Light Fixture Installation Throughout
    Complete Fire Alarm Pre-Wire Installation
    Start Ceramic Tile Installation
    Electrical Prep for Shut-Down / Switchgear Installation Starting 11-21
Excavation 1.jpg
    Continue Refrigerant Piping Extension to Condensers

Start Fire Alarm Pre-Wire Installation

Excavation 1.jpg

Install Light Fixtures Throughout Basement