Weekly Project Update
Hill Country Bible Church

James Castillo
Jun 24, 2021
THIS WEEK'S ACCOMPLISHMENT
- poured concrete approach at West San Gabriel
- Started duct work at East worship space
-
-
-
-

NEXT WEEK'S ACTIVITIES
- Start stone wainscot
- Asphalt for temp FIRE/EMS access
- continue MEP at East worship space
- pour RTU house keeping pads
- Start metal fascia and gutters

-

LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.