Weekly Project Update
Hillcrest Elementary School Secure Vestibule

Tommy McDow
THIS WEEK'S ACCOMPLISHMENT
- Continued Installing Pathways For Access Control and Cameras
- Framed New Wall for Acoustical Panels
- Installed Pathways For Fire Alarm
- Continued Installing Lighting Controls
-
-

Framing For Acoustical Fur-Down
NEXT WEEK'S ACTIVITIES
- Complete Access Control Pathways
- Survey Canopy Footings and Concrete Flat Work
- Sheetrock New Tile Wall and Acoustical Wall
- Begin Installing Concrete Forms and Steel Reinforcing
-

-
Electrical, Access Control, And Fire Alarm Pathways

Framing for New Interior Storefront Doors
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.