Weekly Project Update

Hillcrest

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    Set 60% of columns for canopy
    temp covered all openings and column bases
Excavation 1.jpg

Columns from front approach

NEXT WEEK'S ACTIVITIES

    Concrete work to allow for remaining columns to be set
    Complete setting all columns
    Begin beam installation
Excavation 1.jpg

High canopy at school entrance

Excavation 1.jpg

View of Canopies C and A at parent drop off

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.