Weekly Project Update
Hillcrest

Sid Wegert
THIS WEEK'S ACCOMPLISHMENT
- Remaining columns installed and grouted
- Structural beam installation complete on canopies B and C
- Structural beam installation ongoing Canopy A
-
-
-

Remaining Columns installed
NEXT WEEK'S ACTIVITIES
- Complete beam installation on canopies A and D
- Get decking material onsite
- Begin decking Canopy D
-
-

-
Framing started

Overall canopy view from street
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.