top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

MARTIN CRUMPTON OFFICE RENOVATION

Placeholder

Pat Tims

THIS WEEK'S ACCOMPLISHMENT

    MILLWORK SECOND COAT COMPLETED
    ADHESIVE REMOVAL 95% COMPLETE
    SECOND COAT OF PAINT COMPLETED
    DATA CABLING COMPLETED
Excavation 1.jpg

DATA CABLING INSTALLATION

NEXT WEEK'S ACTIVITIES

    MILLWORK PAINT COMPLETED
    CARPET INSTALLATION
    PAINT COMPLETED
    FINAL CLEAN
Excavation 1.jpg

CARPET ADHESIVE REMOVAL UNDERWAY

Excavation 1.jpg

MILLWORK SECOND COAT COMPLETED

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page