Weekly Project Update

MNTHS

Placeholder

Richard Huddleston

THIS WEEK'S ACCOMPLISHMENT

    Removed rainwater from grade beams.
    Received rebar for new driveway.
Excavation 1.jpg

Forming driveway and sidewalk intersection.

NEXT WEEK'S ACTIVITIES

    Adjust forms to match new man door locations.
    Dig relief trenches at grade beams to minimize standing water for upcoming rain Thursday and Monday.
Excavation 1.jpg

Forming cubs at new driveway.

Excavation 1.jpg

Using submersible pumps to remove rainwater from grade beams.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.