top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

MNTHS

Placeholder

Richard Huddleston

THIS WEEK'S ACCOMPLISHMENT

    Installed void form boxes, vapor barrier, rebar and formed the inside of grade beam on grid line A, 10, 10.5 and 11.
    Install soil retainers on the inside of grade beams 1 & I.
    Poured concrete in grade beams on grid lines A,10, and 10.5.
Excavation 1.jpg

began the installation of rebar and vapor barrier at the viewing platform and column line 10.

NEXT WEEK'S ACTIVITIES

    Complete soil retainers on the inside at grid lines A, And 10.
    Backfill and do density test on the field side of grade beams A,1,I, and 10.
    Clear off field area so final base can be installed the following week.
Excavation 1.jpg

Placing concrete in the south east corner grade beams.

Excavation 1.jpg

Placing concrete on the north end of grid line 10 with a pump truck.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.