THIS WEEK'S ACCOMPLISHMENT
- Installed void form boxes, vapor barrier, rebar and formed the inside of grade beam on grid line A, 10, 10.5 and 11.
- Install soil retainers on the inside of grade beams 1 & I.
- Poured concrete in grade beams on grid lines A,10, and 10.5.
-
-
-

began the installation of rebar and vapor barrier at the viewing platform and column line 10.
NEXT WEEK'S ACTIVITIES
- Complete soil retainers on the inside at grid lines A, And 10.
- Backfill and do density test on the field side of grade beams A,1,I, and 10.
- Clear off field area so final base can be installed the following week.
-
-

-
Placing concrete in the south east corner grade beams.

Placing concrete on the north end of grid line 10 with a pump truck.