Weekly Project Update

MNTHS

Placeholder

Richard Huddleston

THIS WEEK'S ACCOMPLISHMENT

    Received the balance of the steel structure for the building..
    Began building the rafters on the ground to create workspace for erecting.
    Began standing columns on the NW corner.
Excavation 1.jpg

Standing steel at the NW corner.

NEXT WEEK'S ACTIVITIES

    Continue standing steel on the west gridline.
    Bluebonnet Electric cover powerline nearest the SE corner of the building
    Stand steel on the south gridline parallel to Old Hwy 20.
Excavation 1.jpg

Building rafters on the ground to create workspace for erecting the building.

Excavation 1.jpg

Building the NW Portal that's designed to brace the building.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.