Weekly Project Update
MNTHS

Richard Huddleston
THIS WEEK'S ACCOMPLISHMENT
- Installed columns and girts on southside of the building.
- Installed columns and girts on the eastside of the building.
- Installed eave frame at the top of the east wall.
-
-
-

Installing columns with a crane on the SE corner.
NEXT WEEK'S ACTIVITIES
- Install permanent bracing in walls.
- Begin building roof bays on the ground starting from the south.
-
-
-

-
Installing columns and girts on the south wall.

90% of the walls are up ready for permanent bracing.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.