Weekly Project Update

MNTHS

Placeholder

Richard Huddleston

THIS WEEK'S ACCOMPLISHMENT

    Installed columns and girts on southside of the building.
    Installed columns and girts on the eastside of the building.
    Installed eave frame at the top of the east wall.
Excavation 1.jpg

Installing columns with a crane on the SE corner.

NEXT WEEK'S ACTIVITIES

    Install permanent bracing in walls.
    Begin building roof bays on the ground starting from the south.
Excavation 1.jpg

Installing columns and girts on the south wall.

Excavation 1.jpg

90% of the walls are up ready for permanent bracing.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.