Weekly Project Update

MNTHS

Placeholder

Richard Huddleston

THIS WEEK'S ACCOMPLISHMENT

    Survey team staked building corners and piers..
    Delivered Storm drainpipe and new fire hydrant.
    Delivered rebar for piers.
    Installed batter boards (wood framing to set string lines to mark edge of perimeter concrete)
    Installed base to subgrade at new driveway approach at Old Hwy 20.
    Scheduled drilling rig and testing lab to be onsite Mon- Fr. of next week.
Excavation 1.jpg

1st delivery of rebar for the piers.

NEXT WEEK'S ACTIVITIES

    Tie rebar cages for piers.
    Drill, inspect and pour piers on grid line 1.
    Start piers on gridline A
    Start storm drainpipe installation.
Excavation 1.jpg

Storm drainpipe being delivered.

Excavation 1.jpg

Installing base material at the new driveway approach off of Old Hwy 20 at the SE corner of the project.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.