Weekly Project Update

Manor ISD Kitchen Serving Lines (Manor High School)

Placeholder

Stephen Bates

THIS WEEK'S ACCOMPLISHMENT

    Under slab plumbing rough complete
    Plumbing under slab inspections passed
    Under slab electrical complete
    Electrical under slab inspections passed
    Ceiling grid installation started in back area
    Framing started at columns and front wall in cafeteria
Excavation 1.jpg

Underground electrical rough complete

NEXT WEEK'S ACTIVITIES

    Backfill plumbing and electrical underground rough
    Set carton forms, start bending back and tying rebar
    Continue wall framing
    Electrical and plumbing wall rough
    Continue ceiling grid
Excavation 1.jpg
    Concrete pour back

Ceiling grid started in back area

Excavation 1.jpg

Under slab plumbing rough complete and inspections passed

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.