Weekly Project Update
Manor ISD Kitchen Serving Lines (Manor High School)

Stephen Bates
THIS WEEK'S ACCOMPLISHMENT
- Under slab plumbing rough complete
- Plumbing under slab inspections passed
- Under slab electrical complete
- Electrical under slab inspections passed
- Ceiling grid installation started in back area
- Framing started at columns and front wall in cafeteria

Underground electrical rough complete
NEXT WEEK'S ACTIVITIES
- Backfill plumbing and electrical underground rough
- Set carton forms, start bending back and tying rebar
- Continue wall framing
- Electrical and plumbing wall rough
- Continue ceiling grid

- Concrete pour back
Ceiling grid started in back area

Under slab plumbing rough complete and inspections passed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.