Weekly Project Update

Manor ISD Kitchen Serving Lines (Manor High School)

Placeholder

Stephen Bates

THIS WEEK'S ACCOMPLISHMENT

    Ceiling grid complete
    Structural steel inspected and corrections made
    Carton forms set and vapor barrier installed
    Rebar bent back and splicing complete
    Rebar inspections passed
    Concrete inspections called in for Tuesday
Excavation 1.jpg

Ceiling grid complete

NEXT WEEK'S ACTIVITIES

    Pour back concrete
    Call in framing inspections
    Install wallboard
    Layout for new kitchen equipment and start tile
    Continue above ceiling rough in
Excavation 1.jpg

Structural steel inspected and corrections made

Excavation 1.jpg

Rebar inspected and ready for concrete Tuesday

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.