THIS WEEK'S ACCOMPLISHMENT
- Ceiling grid complete
- Structural steel inspected and corrections made
- Carton forms set and vapor barrier installed
- Rebar bent back and splicing complete
- Rebar inspections passed
- Concrete inspections called in for Tuesday

Ceiling grid complete
NEXT WEEK'S ACTIVITIES
- Pour back concrete
- Call in framing inspections
- Install wallboard
- Layout for new kitchen equipment and start tile
- Continue above ceiling rough in

-
Structural steel inspected and corrections made

Rebar inspected and ready for concrete Tuesday