Weekly Project Update
Manor ISD Kitchen Serving Lines (Manor High School)

Stephen Bates
THIS WEEK'S ACCOMPLISHMENT
- Overhead doors installed
- Vinyl flooring installed
- Texture and paint completed on cafeteria wall
- Ceiling grid complete
- Grilles and lights set ready for inspections
- Old kitchen equipment moved in

Vinyl flooring installed
NEXT WEEK'S ACTIVITIES
- Above ceiling inspections
- Set serving lines
- Hook up all equipment
- Fix trim at OH doors
- MEP final inspections

- Final clean
Texture, paint and ceiling tile complete on cafeteria side

Serving line equipment installing
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.