Weekly Project Update
Manor ISD Kitchen Serving Lines (Manor High School)

Stephen Bates
THIS WEEK'S ACCOMPLISHMENT
- All rebar inspected and concrete tested by testing labs
- Concrete pour back complete
- New serving line equipment laid out and ready for tile and vinyl flooring
- Framing and wall rough inspection passed
- Wall board installation in progress
- Tile started on walls and floors

Concrete pour back complete
NEXT WEEK'S ACTIVITIES
- Continue wall tile
- Install overhead doors
- Finish installing wallboard
- Start tape and float
- Install Vinyl flooring

- Get back area ready for above ceiling inspection and start tile
Wall board and wall tile started

Floor tile started
LOOK AHEAD SCHEDULE