THIS WEEK'S ACCOMPLISHMENT

    Above ceiling inspections passed
    All serving lines set
    All equipment hooked up
    Fire Final Passed
    Final Clean complete
    Ceiling tile installed
Excavation 1.jpg

NEXT WEEK'S ACTIVITIES

    MEP final inspections
    Building Final
    Health Inspection
    Punch Walk
    Complete punch Walk items
Excavation 1.jpg
    Walk with District

Excavation 1.jpg

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.