Weekly Project Update

Manor New Tech

Placeholder

Richard Huddleston

THIS WEEK'S ACCOMPLISHMENT

    Removed exiting asphalt from the old school bus parking lot.
    Compacted existing soil beneath the future building and had Terra Testing come out and verify density.
    Brought in structural fill to be processed and compacted to get the soil level up to sub grade.
Excavation 1.jpg

Removing the old concrete entrance at Hwy 20.

NEXT WEEK'S ACTIVITIES

    Continue building the building pad.
    Mobilize the utility contractor to get utilities across the new fire lane.
Excavation 1.jpg

Loading the asphalt that was removed from the parking lot.

Excavation 1.jpg

Spreading the first layer of structural fill to be compacted.