Weekly Project Update
Manor New Tech

Richard Huddleston
THIS WEEK'S ACCOMPLISHMENT
- Brought in more base material to complete the second lift on the building pad.
- Passed soil density test on second lift.
- Building pad below meeting rooms is up to finished subgrade.
-
-
-

Concrete at the old entry off of Hwy 20 is removed.
NEXT WEEK'S ACTIVITIES
- Continue bringing in base material to raise the building pad at the turf area to finished subgrade.
- Once approved submittals are returned, my utility sub-contractor will mobilize and deliver material for installation.
-
-
-

-
Compacting the second lift of base material, preparing for density test.

Soil below the meeting rooms is at subgrade elevation and has passed density test.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.