top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Manor New Tech

Placeholder

Richard Huddleston

THIS WEEK'S ACCOMPLISHMENT

    Brought in more base material to complete the second lift on the building pad.
    Passed soil density test on second lift.
    Building pad below meeting rooms is up to finished subgrade.
Excavation 1.jpg

Concrete at the old entry off of Hwy 20 is removed.

NEXT WEEK'S ACTIVITIES

    Continue bringing in base material to raise the building pad at the turf area to finished subgrade.
    Once approved submittals are returned, my utility sub-contractor will mobilize and deliver material for installation.
Excavation 1.jpg

Compacting the second lift of base material, preparing for density test.

Excavation 1.jpg

Soil below the meeting rooms is at subgrade elevation and has passed density test.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page