Weekly Project Update
Manor Senior High School Gym and MPB

Gary Fritz
THIS WEEK'S ACCOMPLISHMENT
- Completed all demo and haul off at the MPB
- Started excavation for the fire/water line at the GYM
- Started excavation and installation of Storm Drain line at GYM
- Received delivery of piping and man holes
-
-

Storm Drain Install
NEXT WEEK'S ACTIVITIES
- Continue with installation of storm drain line and manholes at GYM
- Continue with excavation of water/fire line
- Start clear and grub at the MPB
- Start foundation prep for slab on grade at the MPB
-

-
Storm Drain piping

Area for SOG prep