Weekly Project Update

Manor Senior High School Practice Gym and MPB

Placeholder

Gary Fritz

THIS WEEK'S ACCOMPLISHMENT

    Paving at Gym parking complete
    Opened up main parent drop off road
    First grade beam at MPB ready for inspection and concrete
    Drilling last 48" pier at MPB
    Grade beams at Gym moving fast
Excavation 1.jpg

Grade beams at MPB

NEXT WEEK'S ACTIVITIES

    Continue grade beams at Gym
    Continue grade beam installation at MPB
    Drill remaining pier at Gym
Excavation 1.jpg

Paving at Gym

Excavation 1.jpg

Paving at Gym

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.