Weekly Project Update
Manor Senior High School Practice Gym and MPB

Gary Fritz
THIS WEEK'S ACCOMPLISHMENT
- Sub grade at gym is complete, tested and passed
- All but two piers complete at MPB
- Grade beams at MPB underway
- Layout and batter boards at Gym is underway
-
-

Forming grade beams at MPB
NEXT WEEK'S ACTIVITIES
- Start pier drilling at Gym foundation
- Continue grade beam installation at MPB
- Complete last two piers at MPB
-
-

-
Forming grade beams at MPB

Setting batter boards and layout of Gym foundation
LOOK AHEAD SCHEDULE