top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Manor Senior High School Practice Gym and MPB

Placeholder

Gary Fritz

THIS WEEK'S ACCOMPLISHMENT

    Sub grade at gym is complete, tested and passed
    All but two piers complete at MPB
    Grade beams at MPB underway
    Layout and batter boards at Gym is underway
Excavation 1.jpg

Forming grade beams at MPB

NEXT WEEK'S ACTIVITIES

    Start pier drilling at Gym foundation
    Continue grade beam installation at MPB
    Complete last two piers at MPB
Excavation 1.jpg

Forming grade beams at MPB

Excavation 1.jpg

Setting batter boards and layout of Gym foundation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page