Weekly Project Update
Marble Falls Region 13

Nathan Stanford
THIS WEEK'S ACCOMPLISHMENT
- Started metal stud framing
- Started hanging new duct. 95% of duct arrived from Houston.
- Electrical rough in continues 50%
- Lowered shower floor in existing slab
- Plumber rough in 25%
- Completed low voltage demo for owner. All demo now 95%

Plumbing bathroom wall framed and plumbing rough in installed
NEXT WEEK'S ACTIVITIES
- Metal stud and sheet rock continue
- Inspections on wall rough ins scheduled.
- Plumbing wall rough in to be 95%
- Electrical wall rough in to be 99%
- Hang 80% f duct now on ground.

- Get insulation to site for ducts and plumbing piping.
Storage room walls installed with electrical getting roughed in.

Large training area with duct getting installed. Lots of duct on ground ready to install.