Weekly Project Update

Marble Falls Region 13

Placeholder

Nathan Stanford

THIS WEEK'S ACCOMPLISHMENT

    Started metal stud framing
    Started hanging new duct. 95% of duct arrived from Houston.
    Electrical rough in continues 50%
    Lowered shower floor in existing slab
    Plumber rough in 25%
    Completed low voltage demo for owner. All demo now 95%
Excavation 1.jpg

Plumbing bathroom wall framed and plumbing rough in installed

NEXT WEEK'S ACTIVITIES

    Metal stud and sheet rock continue
    Inspections on wall rough ins scheduled.
    Plumbing wall rough in to be 95%
    Electrical wall rough in to be 99%
    Hang 80% f duct now on ground.
Excavation 1.jpg
    Get insulation to site for ducts and plumbing piping.

Storage room walls installed with electrical getting roughed in.

Excavation 1.jpg

Large training area with duct getting installed. Lots of duct on ground ready to install.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.