Weekly Project Update

Marble Falls Region 13

Placeholder

Nathan Stanford

THIS WEEK'S ACCOMPLISHMENT

    Ceramic tile completed Waiting on grout colors
    ! of 2 curbs for outdoors RTU arrived
    Grid installed 75% waiting on parts
    Some duct for RTU installed Waiting on more duct
    Grilles installed in grid 75% Some Fire alarm devices installed
    Brick openings in masonry completed
Excavation 1.jpg

Long awaited curb arrived

NEXT WEEK'S ACTIVITIES

    Waiting on 2nd RTU curb Waiting on VAV's
    Window painting
    Waiting on lights and lighting control
    Waiting on doors and hardware
    Millwork should set
Excavation 1.jpg
    Minor duct and electrical

Some duct thru exterior walls started

Excavation 1.jpg

Fire alarm and some grilles installed in some grid.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.