top of page


Weekly Project Update
Marble Falls Region 13

Nathan Stanford
THIS WEEK'S ACCOMPLISHMENT
- Ceramic tile completed Waiting on grout colors
- ! of 2 curbs for outdoors RTU arrived
- Grid installed 75% waiting on parts
- Some duct for RTU installed Waiting on more duct
- Grilles installed in grid 75% Some Fire alarm devices installed
- Brick openings in masonry completed

Long awaited curb arrived
NEXT WEEK'S ACTIVITIES
- Waiting on 2nd RTU curb Waiting on VAV's
- Window painting
- Waiting on lights and lighting control
- Waiting on doors and hardware
- Millwork should set

- Minor duct and electrical
Some duct thru exterior walls started

Fire alarm and some grilles installed in some grid.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page